Siyoi Muruny' Dam- West Pokot County

Siyoi Muruny’ Dam
Siyoi Muruny’ Dam Project is located in West Pokot County,
42km to the west of Kapenguria Town. The water treatment works are located at
Kabichbich Town and about 11km from the dam.
The project will supply potable water to a population of
350,000 persons by year 2035. The project covers Kapenguria Municipality,
Kabichbich Township, parts of Chepareria and areas along the pipeline route
from Kabichbich to Kapenguria.
Construction of the project started in 2015 and was
scheduled to be complete in March 2018 after three years construction period.
However, there have been several extensions of time owing to delays majorly
caused lack of adequate and consistent funding funds for the project.
The project is divided into two components for ease of
implementation: Lot 1 (Dam component) and Lot 2 (Water Supply Component).
Current Status of project
The implementing Contractor is M/s China Jiangxi
International Kenya Limited.
Project supervision is being carried out by National Water
Harvesting and Storage Authority team of Engineers lead by a Resident Engineer.
This new supervision arrangement came into being after expiry of the contract
of the supervising consultant on 16th April 2021.
Physical Status
The Overall progress of this Component is 55.5%.
The detailed progress of the activities is as indicated
below:
- 30m
high dam embankment structure complete: – 10% complete
- 180m
long spillway; – 98% Complete
- 32m
high intake tower; – 95% complete
- 71m
long bridge across reservoir and 15m long bridge across spillway; -60%
complete
- 184m
long twin diversion culvert; -98% complete
- 8km
road across dam embankment; -60% complete
- Road
diversion of 900m long at 71m long bridge; -60% complete
- 11km
long, 800mm diameter steel pipeline; -36% complete
- 10km
fence round the dam and reservoir; – 0% complete
- Community
water projects and CSR projects costing a total of KShs.250million: -0%
complete.
Ongoing work
Ongoing works include the following:
- Laying
of pipeline inside diversion culvert has been completed (185m). The
pipeline laying is continuing beyond the diversion culvert but currently
being affected by rains;
- Fittings
to intake tower have been supplied, work is ongoing and is 80% complete;
- Construction
of drainage culverts across valleys on raw water pipeline are 20%
complete. 3No. culverts have been completed out of 12No.;
- Extension
works for Foot Bridge from pier No. 5 is 80% complete. Casting of slab
together with guard rail embedded parts is being planned;
- culverts
on Access Road have been completed and 1No. is pending construction.